Skip to main content
HVDC - High Voltage Direct Current
TenneT BorWin 6
1,030MW HVDC

marine station

17,500 t

topsides Wt

9,300 t

jacket

35–40 m

water depth

Onshore converter

station

Scope
EPFIC Lump Sum Turnkey
Location
Offshore Germany
Highlights
  • Engineering, procurement, fabrication, transportation, installation and commissioning of the topside module (converter station), including jacket and piling installation
  • Fabrication carried out at McDermott’s Jebel Ali facility in Dubai

Through a consortium with Global Energy Interconnection Research Institute Co., Ltd. (GEIRI) and C-EPRI Electric Power Engineering Co., Ltd. (CEPRI), we are delivering full EPCIC services for an HVDC offshore converter platform located off the coast of Germany. Electricity generated by offshore wind farms will be converted from AC to DC power and transported to an onshore converter station located 146 miles (235 kilometers) onshore near Büttel. There, the electricity will be converted back into three-phase current and fed into the countries grid system.